Management Review Procedure
How ASF's leadership steps back, at least once a year, to ask whether the whole system is actually working
Foreword
An internal audit, under the ASF Internal Audit Procedure, checks whether a specific process was followed correctly. It does not ask a bigger question: taken together, is the whole system actually working, improving, and adequately resourced? That is what management review is for — a distinct, mandatory function under both ISO 9001 Clause 9.3 and the management-system requirements of ISO/IEC 17011, and one ASF has not, until this document, formally committed to on a defined schedule [1–2].
1. Purpose and Frequency
The ASF International Standards Council conducts a formal management review at least once every calendar year, examining ASF's operations as a whole rather than any single process in isolation. This is deliberately more frequent than the three-year standards revision cycle and the internal audit program, because a leadership-level check on whether the system is working should not wait as long as a full technical revision does.
2. Why Genuine Review Matters: The Real Evidence
This procedure is not built on the assumption that holding a meeting called “management review” is itself valuable. Real research on governance effectiveness shows the gap between a genuine review and a procedural one is measurable. McKinsey research on board effectiveness found that fifty-nine percent of directors at top-quartile boards report their organization significantly outperformed its peers, compared with only forty-three percent at bottom-quartile boards — a real, substantial gap tied directly to the quality of governance oversight itself, not merely to the underlying business [3].
More specifically relevant to how this procedure is structured, a large annual survey of C-suite executives found that nine out of ten believe their organization's review and assessment process could be meaningfully improved — and the most commonly cited improvement was using reviews not merely to assess performance, but to drive genuine follow-through and action [4]. The same research found that a significant share of executives specifically wanted clearer follow-through on issues raised during a review, not merely a well-run discussion of them [4]. This is precisely why Section 4 of this procedure treats documented outputs and decisions as the actual point of a management review, not an optional closing formality.
3. Review Inputs
Consistent with the real inputs ISO 9001 Clause 9.3 requires a management review to actually consider, not merely acknowledge in passing, each annual review examines [1]:
- The status of actions arising from the previous management review — were they actually completed, not merely recorded as planned
- Findings from every internal audit conducted since the last review, under the ASF Internal Audit Procedure, including any pattern across multiple audits' observations
- The outcome of the most recent external review under Section 7.5 of How ASF Develops and Revises Standards
- Aggregate sentinel event data and trends, under the ASF Sentinel Event Policy's own aggregate learning function
- Public complaint volume, substantiation rate, and response-time compliance, under the ASF Public Complaints & Feedback Policy
- Any nonconformity and corrective action opened under the ASF Internal Nonconformity & Corrective Action Procedure, and whether corrective actions were verified as effective
- Whether ASF's current resources — staff, surveyor capacity, financial position — remain adequate for the volume and complexity of ASF's actual current operations
- Genuine opportunities for improvement identified through any of the above, not limited to problems already formally raised
4. Review Outputs
A management review that produces no decisions has not actually reviewed anything. Consistent with ISO 9001's own requirement that management review produce genuine outputs, not just a record that a meeting occurred [1], each review produces documented decisions on:
- Any opportunity for improvement the Council has decided to act on, and by when
- Any need to change ASF's own management system — including this procedure, the Internal Audit Procedure, or any other governance document — identified through the review
- Any resource need identified as genuinely necessary, with a decision on how it will be addressed
5. Relationship to Other ASF Processes
- Internal audit (ASF Internal Audit Procedure) feeds findings into management review; management review does not replace or repeat the audit itself
- External review (Section 7.5 of How ASF Develops and Revises Standards) feeds its outcome into management review as one input among several, not as a substitute for ASF's own internal reflection
- A specific nonconformity is corrected through the ASF Internal Nonconformity & Corrective Action Procedure; management review examines the pattern those corrections form over time, not the individual correction itself
References
- International Organization for Standardization. ISO 9001:2015, Quality Management Systems — Requirements, Clause 9.3 (Management Review). Geneva: ISO; 2015.
- International Organization for Standardization. ISO/IEC 17011:2017, Conformity Assessment — Requirements for Accreditation Bodies Accrediting Conformity Assessment Bodies. Geneva: ISO; 2017.
- Board Intelligence, citing McKinsey research on board effectiveness and organizational outperformance. How to Effectively Manage a Board of Directors. 2026.
- PwC and The Conference Board. Board Effectiveness: A Survey of the C-Suite. Governance Insights Center. 2026.
Annex A — Management Review Record
Review period covered: ______________________________
Date of review: ______________________________
Council members present: _____________________________________________
Inputs Considered
☐ Status of prior review's actions
☐ Internal audit findings since last review
☐ External review outcome (if applicable this period)
☐ Sentinel event aggregate data
☐ Public complaint data
☐ Nonconformity and corrective action status
☐ Resource adequacy
Decisions and Actions
_______________________________________________________________________
_______________________________________________________________________
Next review scheduled for: ______________________________
Index
Annual Frequency, 1
Board Outperformance (real evidence), 2
Follow-Through (real gap), 2, 4
Review Inputs, 3
Review Outputs, 4
Top-Quartile vs Bottom-Quartile Boards, 2
This procedure exists so that ASF's leadership examines the whole system at least as often as the system asks organizations it accredits to examine themselves — and produces real decisions when it does, not merely a well-documented conversation.
| Document Title | ASF Management Review Procedure |
| Document Reference | ASF-MGMTREVIEW-001-v2 |
| Version / Edition | Version 2 |
| Status | Published |
| Date of Publication | 12 September 2026 |
| Place of Publication | Paris, France |
| Issuing Authority | ASF International Standards Council, Accréditation Sans Frontières |
| Language of Origin | English |
| Effective Date | 12 September 2026 |
| Next Scheduled Review | 12 September 2029 |
| Supersedes | Version 1 |
Have a question about this document?
Corrections, translation requests and proposals for the next revision cycle are welcome from anyone.