Purpose
Records each back-up test and each real switch to back-up.
How to complete
- Test each back-up on the schedule.
- Record each real switch.
- Record the time to switch.
Record fields
| Date | Back-up (power, line, system, equipment) | Test or real switch | Time to switch | Passed (yes or no) | Action |
|---|---|---|---|---|---|
Evidence
| Reference | Note |
|---|---|
| E-009 | ASF Expert Committee consensus. |
| E-006 | ASF Policy Framework v1.2. Adapted. |
| E-009 | ASF Expert Committee consensus. |
Change history
| Version | Date | What changed | Approval |
|---|---|---|---|
| 1.0 | the date of approval | First version | set Expert Committee approval |
E-learning for this document
References
- Accréditation Sans Frontières (2026). ASF Policy Framework v1.2. (E-006)